Authomathika started the construction work of Fazenda Velha PCH in November 2015. Built in the bed of Ribeirão Ariranha and located in the municipality of Jataí, State of Goiás.

Extending the area of activity in the market, Authomathika began the electromechanical assembly of the Fazenda Velha PCH, investing in an exclusive technical body for the implementation of new sources of electricity generation in the water sector.

Our scope consists of the supply of electromechanical projects, lighting project, materials and specialized labor for electromechanical assembly of powerhouse, water intake, 69kV substation and connection points. The installed generation capacity is 16.5MW.

The completion and startup of this PCH occurred in mid-June 2016 with the commercial operation of the three generating units in full operating capacity.