Solar photovoltaic plants

Centralized Solar Generation: How It Works

Learn how centralized solar generation works at utility scale, how it differs from distributed generation, and what grid connection and electrical systems it needs.

Direct answer

Centralized solar generation is a utility-scale photovoltaic plant that produces power at one site and delivers it through a step-up substation to the transmission or subtransmission grid. Unlike distributed generation, it does not serve a local load first. Authomathika has installed more than 890 MW of solar across 10 photovoltaic parks.

Institutional content: Authomathika

Published:

Centralized solar generation concentrates a large photovoltaic plant at a single site, usually far from the loads it supplies. The electrical design is closer to a power station than to a rooftop system. Understanding this model helps engineering, projects and maintenance teams specify the plant and its connection correctly.

What is centralized solar generation?

Centralized solar generation is a photovoltaic plant built at utility scale, where all the energy produced is collected at one point and injected into the grid through a dedicated substation. Its purpose is to supply the system, not a nearby consumer.

The plant is made of photovoltaic modules, strings, inverters, medium voltage collection circuits, a step-up transformer and a point of interconnection. In Brazil these plants are commonly called UFV. If you want the terminology in detail, see What Is a UFV? Solar Power Plant Terminology.

How does it differ from distributed generation?

The main difference is where the energy goes and at what voltage it connects. Distributed generation is installed at or near the consumer and connects to the distribution network at low or medium voltage. Centralized generation is a standalone producer connected at higher voltage, with its own substation.

AspectCentralized generationDistributed generation
LocationDedicated site, often remoteAt or near the load
Main destination of energyThe gridThe local load first, surplus to the grid
Connection voltageMedium voltage collection, high voltage exportLow or medium voltage
SubstationOwn step-up substationUsually none, or a small transformer
Grid studies and operator coordinationExtensiveSimpler
Control and monitoringPlant level SCADA, operator data exchangeInverter level monitoring

The boundary between the two models depends on the regulation in force in each country, so check the current rules that apply to your project.

What electrical infrastructure does a centralized plant require?

A centralized plant requires a chain of equipment that collects direct current from the modules, converts it, raises the voltage and delivers it to the grid. Each stage has its own protection, measurement and documentation.

The typical chain is:

  1. Photovoltaic modules wired in strings, with direct current cabling and combiner boxes.
  2. Inverters, central or string type, that convert direct current to alternating current.
  3. Step-up transformers at the inverter stations, raising to medium voltage.
  4. Medium voltage collection circuits and switchgear that gather the output of all arrays.
  5. The plant substation, with the main step-up transformer, protection and measurement.
  6. The grounding system and lightning protection for the whole area.
  7. Control, SCADA and communication systems that tie everything together.

The supervision layer is a topic of its own, covered in Solar Plant SCADA and Monitoring: What to Integrate. For the overall plant concept, see Solar PV Plant: What It Is and How It Works.

How is the connection to the transmission or distribution grid made?

The connection is made at a point of interconnection, defined with the grid operator after access studies, through the plant substation and a connection line or bay. The operator sets the technical requirements the plant must meet.

In practice, the process involves these steps:

  1. Request for grid access and technical studies with the operator.
  2. Definition of the point of interconnection and the connection voltage.
  3. Basic and executive design of the substation and connection facilities.
  4. Protection settings and coordination with the operator's system.
  5. Revenue metering and data exchange with the operator.
  6. Energization tests and approval before commercial operation.

The operator typically evaluates behavior such as protection response, voltage and frequency support, and communication. Requirements change over time and by operator, so consult the grid code and the current edition of the applicable standards. The last steps overlap with commissioning, explained in What Is Solar Plant Commissioning and When It Starts.

What engineering care changes at large scale?

At large scale, small design choices repeat thousands of times, so standardization, cable routing, protection and construction logistics weigh much more. The engineering moves from equipment selection to system integration.

Key points to review:

  • Voltage drop and losses in direct current and medium voltage cabling over long runs.
  • Short circuit levels and protection coordination between inverters, collection circuits and the substation.
  • Grounding design for a large area, with attention to step and touch voltages.
  • Communication architecture between inverters, trackers, meters and the control room.
  • Civil and electromechanical interfaces: foundations, trenches, cable trays and access roads.
  • Testing and documentation plan, so that each block can be accepted separately.

Authomathika works with electrical, automation and electromechanical assembly scopes, and has more than 890 MW of solar installed across 10 photovoltaic parks. One example is the UFV Belmonte I & II solar plant, 455 MW, for Grupo Cobra in Pernambuco. You can also read about the company's renewable energy business.

Frequently asked questions

Is centralized solar generation the same as a utility-scale plant?
In practice, yes. Both terms describe a large photovoltaic plant that delivers energy to the grid through its own substation instead of serving a local consumer.
Does a centralized plant always connect to the transmission grid?
Not always. Depending on size and location, it can connect to a subtransmission or distribution network at a higher voltage. The grid operator defines the point of interconnection after access studies.
Why does a centralized plant need its own substation?
The substation raises the voltage from the collection level to the connection level, and houses protection and metering. It also gives the operator a clear point where the plant meets the grid.
What changes in automation compared with a small system?
A centralized plant needs plant level control and supervision, with communication to many inverters, trackers and meters, plus data exchange with the operator. Small systems usually rely on inverter level monitoring only.
Can a project be both distributed and centralized?
No, a given plant falls into one category according to the regulation in force. The classification depends on factors such as capacity, connection voltage and the rules of your country, so confirm them before design.