Electrical Installations Dossier (PIE): What It Must Contain

Learn what the NR-10 electrical installations dossier (PIE) must contain, who keeps it, and how to keep it current, so you can check your own documentation.

Direct answer

The PIE (Prontuário de Instalações Elétricas) is the organized set of documents that NR-10 requires employers to keep for their electrical installations. It covers procedures, diagrams, grounding, specifications, inspection records and worker qualifications, and it must stay current. Authomathika works on electrical installations in industrial plants.

Institutional content: Authomathika

Published:

Brazilian industrial sites are often audited on one question: can the company prove, on paper, that its electrical installations are safe to operate and maintain? The PIE is the main answer to that question under NR-10. This guide explains its purpose, minimum content and upkeep. It is not a ready-made template, and it does not replace the project or the technical judgment of a qualified professional.

What is the electrical installations dossier (PIE)?

The PIE is the documented record of an installation's electrical safety: how it is built, how it is protected, how it is maintained and who is allowed to work on it. NR-10 is the Brazilian regulatory standard for safety in electrical installations and services. It requires employers who operate installations above a defined threshold to keep this dossier organized and available.

Think of the PIE as a living file, not a one-time deliverable. Its job is to let an inspector, a maintenance supervisor or a contractor understand the installation and its risks without guessing. For the broader context of the standard, see NR-10 Explained: What It Is and What It Requires.

Who needs to keep the PIE?

The employer, meaning the company that owns or operates the installation, is responsible for keeping the PIE. Contractors who work on the site should receive the relevant parts and add their own records, but responsibility for the dossier does not transfer to them.

In practice, three groups interact with it:

  • Owner or operator: keeps the complete, current dossier and makes it available to workers and inspectors.
  • Maintenance and engineering teams: feed it with inspection results, test records and drawing updates.
  • Contractors and integrators: deliver as-built documentation and update the sections affected by their work.

Check the current NR-10 text to confirm which installations and which employers fall under the full dossier requirement, and which have a reduced scope.

What documents make up the dossier?

The PIE gathers procedures, drawings, specifications, records and qualification evidence. The table below groups the usual components by purpose. Treat it as a conceptual map and confirm the exact list against the current NR-10.

GroupTypical contentWhy it matters
Procedures and instructionsWork procedures, safety instructions, emergency measuresDefine how work is done safely
Design and drawingsSingle-line diagram, layout, functional diagrams of protection and controlShow how the installation is arranged
SpecificationsCharacteristics of protection devices, equipment and safety systemsSupport selection, replacement and maintenance
Grounding and protectionGrounding and lightning protection documentation, test resultsProve protection against shock and surges
Inspection and test recordsPeriodic inspections, measurements, corrective actionsShow the installation is being verified
Hazardous areasClassification documentation and related records, where applicableSupport correct equipment selection and maintenance
PeopleEvidence of worker training, qualification and authorizationShow who may work on what
Risk analysisRisk assessments and recommendations for the installationLink hazards to controls

A PIE that holds only drawings is incomplete. A PIE that holds only certificates is equally weak. The value lies in the consistency between them.

How do you keep it up to date after plant changes?

The PIE stays valid only if every change to the installation triggers a documentation update. A new feeder, a replaced protection relay, a relocated panel or a changed load all alter what the dossier says.

  1. Register the change. Use a management of change routine so no modification reaches the field without being recorded.
  2. Update the drawings. Revise the single-line diagram, layouts and protection documentation to reflect the as-built condition.
  3. Revise specifications and settings. Record new equipment data and protection settings.
  4. Repeat the affected tests. Grounding measurements, insulation tests and functional checks tied to the change need new records.
  5. Review procedures and risk analysis. A changed installation may change how work must be done.
  6. Revise qualifications. Confirm that the people who will operate or maintain the new equipment are trained and authorized.
  7. Control versions. Keep revision dates, authors and approvals, and withdraw obsolete copies from the field.

How does the PIE connect to the single-line diagram and grounding?

The single-line diagram and the grounding documentation are the two pieces most often checked against the field. The single-line diagram is a simplified drawing showing sources, transformers, busbars, feeders, protection devices and major loads. It tells a reader how power flows and where protection acts.

Grounding documentation shows how the installation is bonded to earth and how protection against shock, fault currents and surges is achieved, along with measurement records. If the diagram shows a feeder that no longer exists, or the grounding records predate a plant expansion, the whole dossier loses credibility.

For medium-voltage installations, the reference standard is ABNT NBR 14039, explained in NBR 14039: Medium-Voltage Installations Standard Explained. For a wider view of related documents, use the Electrical Safety Documentation Checklist for Industrial Sites.

Who can prepare and sign the PIE?

The PIE must be prepared and maintained by qualified professionals, and technical content such as drawings, calculations and tests must be signed by people legally habilitated for that work. The exact requirements, including who must hold what registration, are defined in the current edition of NR-10 and in professional council rules.

As a decision criterion, confirm that whoever signs can answer for what they sign: they should have access to the real installation, know the applicable standards and be able to defend the data in an audit. Authomathika is an engineering integrator working in electrical systems, automation and industrial assembly, and you can learn more on its Electrical page. The dossier itself remains the employer's responsibility.

Frequently asked questions

Is there an official PIE template?
NR-10 defines the minimum content, not a fixed form. Each company organizes the documents in a way that suits its installation, as long as the required items are present, current and accessible.
Can the PIE be digital?
Digital storage is common, provided documents are controlled, versioned, signed where required and available to those who need them, including in an audit. Confirm any formal requirements in the current regulation.
Does a contractor need its own PIE?
Contractors must meet NR-10 requirements for their own workers and activities, and they should receive and update the parts of the site dossier relevant to their work. The owner of the installation remains responsible for the complete PIE.
How often should the PIE be reviewed?
Review it whenever the installation changes, and periodically even without changes, since inspection and test records have their own cycles. Define the review frequency in your own procedures, based on the current standard.
What is the most common PIE failure?
Outdated drawings. After expansions and replacements, the single-line diagram and protection documentation often no longer match the field, which undermines every other document in the dossier.