NR-10 vs NR-35: Differences and When Both Apply

NR-10 vs NR-35 electrical and work at height: compare the risks each Brazilian standard covers and decide when a task needs both controls together.

Direct answer

NR-10 covers safety in installations and services with electricity, while NR-35 covers work at height. They control different risks, so they are not alternatives. A task such as servicing equipment on an elevated structure near energized parts needs both, plus a risk analysis and trained, authorized people.

Institutional content: Authomathika

Published:

Plant managers often ask whether NR-10 or NR-35 governs a given job. The honest answer is that they answer different questions: one is about electricity, the other about falls. In industrial maintenance and construction, many tasks sit where the two overlap.

This guide compares the two standards by the risk they control and shows field situations where both apply. It guides decisions and does not replace the text of the standards, a project, or the procedures of your plant. Always consult the current edition of each standard.

What does each standard cover?

NR-10 is the Brazilian regulatory standard for safety in electrical installations and services. It applies to generation, transmission, distribution and consumption of electricity, including design, construction, assembly, operation and maintenance. NR-35 is the Brazilian regulatory standard for work at height. It sets requirements for planning, organizing and carrying out work at height so that workers are protected from falls and their consequences.

In short, NR-10 is defined by the energy source (electricity) and NR-35 by the work position (height). A job can trigger one, the other, or both. For a deeper look at the electrical side, see NR-10 Explained: What It Is and What It Requires.

What risks does each one control?

NR-10 controls risks from electrical energy, and NR-35 controls the risk of falling from height. The consequences and the controls are different.

AspectNR-10NR-35
Main hazardElectric shock, electric arc, fire and explosion of electrical originFall of people from height, and fall of objects
Typical controlsDe-energization, locking and tagging, grounding, barriers, safe distances, appropriate tools and PPEAnchor points, fall arrest and restraint systems, rescue planning, access means, area isolation below
Who is affectedPeople working on or near electrical installationsPeople working above the reference level defined by the standard
Core questionIs the circuit energized, and how do we make it safe?Can someone fall, and how do we prevent it or limit the consequence?

The design of the installation itself is a separate topic, covered by technical standards such as ABNT NBR 5410 for low-voltage installations. See NBR 5410: What the Low-Voltage Standard Covers for that scope.

In which industrial services do both apply together?

Both apply whenever a person works on or near electrical parts while positioned at height. The risks do not cancel each other: they add up, and one control can create a problem for the other.

Typical field situations:

  • Maintenance of luminaires, cable trays and conduits on elevated structures or pipe racks.
  • Work on medium-voltage equipment and busbars in substations and electrical rooms where access requires platforms or ladders.
  • Cable pulling and termination on elevated trays during industrial assembly.
  • Installation and inspection of instruments, junction boxes and sensors mounted high on process structures.
  • Cleaning, inspection and repair of solar plant structures and trackers with energized strings.

The interaction matters. A worker who suffers an electric shock at height may fall even from a minor shock. A harness and lanyard made of conductive material, or a metallic ladder, may become a path for electricity. Rescue of a person suspended near energized parts is harder. These conflicts should be solved in planning, not improvised on site.

How does the APR integrate both controls?

The APR (preliminary risk analysis, in Portuguese Análise Preliminar de Risco) is the task-level analysis that identifies hazards and defines controls before the work starts. It is the place where NR-10 and NR-35 controls are reconciled in one plan.

A practical way to build it for a task involving both risks:

  1. Describe the task, the location, the height and the electrical sources nearby.
  2. Identify electrical hazards: energized parts, stored energy, induced voltage, arc flash potential.
  3. Identify fall hazards: edges, openings, fragile surfaces, access route and objects that can fall.
  4. Define how the circuit will be made safe and verified, and who is responsible for it.
  5. Define the access means, anchor points and fall protection, checking compatibility with the electrical environment.
  6. Define the rescue plan for a person at height, including how rescuers act near electrical parts.
  7. Check weather, lighting and simultaneous activities that change the risk.
  8. Record the analysis, brief the team and authorize the start.

When the area also has flammable atmospheres, the classification of the area adds another layer. See Hazardous Area Classification: How It Is Done.

What documents and training does each standard ask for?

Each standard requires its own training and records, and a worker doing a combined task needs the qualifications for both. The exact content, workload and renewal intervals are defined in the current edition of each standard, so confirm them there.

ItemNR-10NR-35
Worker capacityTraining and authorization to work with electricityTraining and capacity to work at height
HealthMedical fitness for the activityMedical fitness for work at height
ProceduresWork procedures and orders for electrical servicesWork procedures and safe work planning
Risk analysisRisk assessment and measures per taskRisk analysis and work permit where applicable
RecordsInstallation documentation, diagrams, inspection recordsEquipment inspection records, training records, rescue plan

When you hire a contractor, ask for evidence of both qualifications for each person assigned to a combined task, plus the procedures they will apply. Also check how the contractor handles equipment, since machine safety follows its own standard, explained in NR-12: Machinery and Equipment Safety Standard Explained.

At Authomathika, electrical and eletromechanical assembly services are scoped and quoted per project. You can see how the company describes its field work on the Montagem Eletromecânica page, and the scope of each service is defined in the proposal.

Frequently asked questions

Is NR-10 or NR-35 more important?
Neither outranks the other. They control different risks, and the task decides which one applies. When a job involves electricity and height, both are mandatory and must be planned together.
Does work on a ladder near a panel need both standards?
If the work is at height as defined by NR-35 and involves electrical installations or parts, both apply. If it is only at floor level, NR-10 alone may apply. Check the definitions in the current edition of each standard.
Can one training course replace the other?
No. NR-10 and NR-35 training have different content and purposes. A worker on a combined task needs the qualification required by each standard, within the validity set in each one.
Does de-energizing the circuit remove the need for NR-35?
No. De-energizing addresses the electrical risk, but the fall risk remains as long as the person works at height. The fall protection and rescue plan are still required.
Where should the combined controls be recorded?
In the APR and in the work procedures of the task, which the plant's safety team approves. The record should show both the electrical measures and the fall protection measures.
Who defines whether a task needs both standards?
The plant's safety engineering and the responsible professionals decide it during task planning, based on the standards and the site procedures. If you need support scoping electrical and assembly services, you can reach out through the contact page.