What Is a Technical Specification and How to Write One

Learn what a technical specification is for industrial equipment and services, which sections it needs, and how to write requirements you can measure and test.

Direct answer

A technical specification is a document that defines what an industrial piece of equipment, material, or service must be and do, with requirements that are measurable and verifiable. It states scope, operating conditions, performance, standards, documentation, and acceptance tests, so any bidder can quote and any buyer can verify delivery.

Institutional content: Authomathika

Published:

A purchase order that says "a pump that fits our process" invites disputes. A technical specification removes that ambiguity by turning a need into requirements that a supplier can price and a buyer can check. This guide defines the document, shows its structure, and explains how to write requirements that hold up at acceptance.

What is a technical specification?

A technical specification is a document that describes the characteristics, performance, and conditions that equipment, material, or a service must meet to be accepted. It is written by the buyer or its engineering team and becomes part of the contract.

A good specification has three properties:

  • Complete enough to quote: two bidders reading it should price the same scope.
  • Verifiable: every requirement can be confirmed by measurement, inspection, test, or document review.
  • Traceable: each requirement connects to a process need, a standard, or a site condition.

It applies to equipment such as a control valve or medium voltage switchgear, and also to services such as assembly, commissioning, or maintenance shutdowns.

What is the difference between a technical and a functional specification?

A functional specification describes what the system must achieve, while a technical specification describes how it must be built or what it must be made of. The first states the result, the second states the means.

AspectFunctional specificationTechnical specification
FocusRequired outcome and behaviorConstruction, materials, ratings, interfaces
Typical contentProcess duty, operating modes, availability goalsDimensions, electrical ratings, protection degree, standards
Supplier freedomHigh, the supplier chooses the solutionLow, the buyer restricts the solution
RiskDifferent bids are hard to compareOver-restriction can block better solutions
Best used whenYou trust the supplier's designYou must match an existing plant or standard

In practice, most industrial documents mix both. State the function first, then restrict the technical choices only where the plant needs it, for example to keep spare parts, protocols, or panel layouts consistent with what you already operate.

Which sections should the document have?

A specification should have the sections below, in an order the reader can follow without jumping between pages. Adapt the list to the item being bought.

  1. Purpose and scope: what is included, what is excluded, and where the supply ends.
  2. Definitions and references: terms, abbreviations, and the documents the specification depends on.
  3. Site and operating conditions: ambient temperature range, altitude, humidity, corrosive atmosphere, area classification, utilities available.
  4. Process or functional requirements: duty, capacity, ranges, operating modes.
  5. Technical requirements: materials, ratings, enclosure protection, interfaces, communication protocols, signals.
  6. Applicable standards: the codes the item must comply with.
  7. Inspection and testing: factory tests, site tests, witness points, acceptance criteria.
  8. Documentation: datasheets, drawings, manuals, test reports, as-built records.
  9. Packaging, delivery, and warranty: transport conditions, spare parts, support after delivery.
  10. Deviations: how a bidder must declare any point it does not meet.

The scope and documentation sections connect directly to contracting. For the paperwork to ask for, see documents to require when contracting industrial projects.

How do you write measurable and testable requirements?

Write each requirement as one statement with a subject, a verb, a measurable value or condition, and a method of verification. If you cannot say how it will be checked, it is not yet a requirement.

Compare:

  • Weak: "The panel must be robust and suitable for the environment."
  • Strong: "The panel enclosure must have the ingress protection degree defined in the datasheet for the installation site, verified by the type test report and visual inspection at the factory."

Rules that keep requirements testable:

  • One requirement per sentence. Compound sentences hide partial failures.
  • Use "shall" for mandatory items and "should" for preferences, and keep that convention throughout.
  • Give units and tolerances, and state the reference conditions for each value.
  • Avoid vague words: "adequate", "high quality", "as needed", "state of the art".
  • Link each requirement to a verification method: inspection, measurement, test, or document review.
  • Put numbers in datasheets, not scattered through the text, so they are easy to update and compare.

Which standards should you cite and how?

Cite a standard when it is the recognized reference for the subject, by its full designation, and state that the edition in force applies unless you name another. Do not copy clauses into the specification; reference the standard and list only the points you need to emphasize or restrict.

Examples of the kind of references that appear in industrial electrical work include NR 10, ABNT NBR 5410, ABNT NBR 14039, and the IEC 61439 series for low voltage assemblies. For machines, NR 12 is the usual Brazilian reference. Your own project, jurisdiction, and equipment type decide which ones apply.

Good practice when referencing:

  • Name the standard and the edition rule in one place, in the references section.
  • Say which party verifies compliance and with what evidence, such as a test report.
  • Define an order of precedence when documents conflict: contract, then specification, then datasheet, then standards.
  • Ask the bidder to list every deviation from the cited standards.

Which mistakes should you avoid when writing?

The most common mistakes are vague wording, missing interfaces, and acceptance criteria that appear only after the order. Each one shifts risk to the buyer at the worst moment.

MistakeConsequenceFix
Vague adjectives instead of valuesBids cannot be comparedState units, ranges, and tolerances
Unclear scope limitsDisputes over who supplies whatDefine the supply boundary and the interfaces
Citing a standard without edition ruleDisagreement about which version appliesState that the edition in force applies, or name it
Copying an old specification unchangedObsolete requirements and contradictionsReview against current site conditions
No acceptance testsNo objective way to reject nonconforming itemsDefine tests, witness points, and criteria
Over-specifying the designBlocks better or cheaper solutionsSpecify function, restrict only where needed
Missing documentation listPlant cannot maintain what it receivedList every deliverable and its format

Before issuing, have operations, maintenance, and procurement read the draft. Each group finds different gaps. A specification is often paired with a terms of reference for the service side and a descriptive memorandum for the solution side.

As an engineering integrator, Authomathika works across electrical, automation, and EPC engineering scopes, where a clear specification defines interfaces between disciplines. Scope and budget are assessed case by case, and you can start through the quote request page.

Frequently asked questions

What is a technical specification in simple terms?
It is a document that tells a supplier exactly what you need and how you will check it. It lists requirements, conditions, standards, tests, and deliverables so the supply can be priced, built, and accepted objectively.
Who is responsible for writing it?
Usually the buyer's engineering team, with input from operations, maintenance, and procurement. A supplier or integrator can help draft it, but the buyer remains responsible for the requirements it signs off.
How detailed should a specification be?
Detailed enough that two bidders would quote the same scope and that every requirement can be verified. Where the plant has no special need, state the function and let the supplier choose the solution.
Is a datasheet the same as a technical specification?
No. A datasheet lists the values for one specific item, while the specification sets the rules, standards, tests, and documentation that apply. The datasheet is normally an attachment to the specification.
Do I need to cite standards in every specification?
Cite them when a recognized standard governs the subject, which is common in electrical and machinery work. Always reference the designation, state the edition rule, and consult the edition in force, since requirements change between editions.