Direct answer
To size a low-voltage main switchboard, collect the load list, apply demand and diversity criteria, define the incoming supply and short-circuit level, then add spare capacity and expansion margin. Document every assumption in the calculation report. Authomathika works from these inputs when it designs industrial panels.
Institutional content: Authomathika
Published:
Sizing a main switchboard is less about a single formula and more about collecting reliable data. A switchboard sized on an incomplete load list or a guessed fault level is either oversized and costly, or undersized and unsafe. This guide covers what the designer must receive before sizing begins.
What design inputs does sizing require?
Sizing requires five groups of data: the load list, the demand criteria, the supply characteristics and short-circuit level, the operating and environmental conditions, and the spare and expansion policy. Without all five, the designer is forced to assume, and assumptions should be recorded, not hidden.
A low-voltage main switchboard (known as QGBT in Brazil) is the assembly that receives power from the transformers or the supply and distributes it to feeders, motor control centers and other panels. If you need the fundamentals first, read What Is an LV Main Switchboard (QGBT) and What It Does.
| Input group | What the designer needs | Typical source |
|---|---|---|
| Loads | Every load, its rated power, voltage and duty | Process and electrical engineering |
| Demand | Operating scenarios and simultaneity | Operations and process teams |
| Supply | Transformer data, source arrangement, grounding system | Single-line diagram, utility data |
| Fault level | Short-circuit study results at the switchboard | Short-circuit study |
| Growth | Spare feeders, space and capacity policy | Plant management, master plan |
How do you build the load list and define demand?
Start with a load list that names each load, its rated power, supply voltage, starting method and duty cycle, then apply demand criteria that reflect how the plant actually operates. The list is the foundation of everything else, so completeness matters more than speed.
A load list is a table of all electrical loads fed by the switchboard, grouped by feeder. Demand is the share of installed load that is expected to run at the same time. Simultaneity depends on the process, not on a generic rule.
Collect these items for each load:
- Tag or identification, and the process area it serves.
- Rated power and voltage.
- Starting method, such as direct on line, soft starter or drive, because it affects inrush and harmonics.
- Duty: continuous, intermittent or standby.
- Whether it is essential, so it can be fed from an emergency or backup source.
- Special conditions, such as non-linear loads or large motors.
How do you define rated current and busbars?
Rated current and busbars follow from the calculated demand at the incoming point, the arrangement of sources, and the conditions in which the assembly will operate. Choose them from the design criteria and the assembly standard, not from a number copied from a similar project.
The designer needs to know how many incomers exist, whether there is a bus coupler, and whether the transformers operate in parallel or separately. Ambient temperature, ventilation of the electrical room and the enclosure arrangement also influence how much current the busbars can carry in service. Enclosure choices are covered in Panel Enclosures: IP Rating, Material and Dimensions.
Criteria to confirm with the assembly manufacturer:
- Rated current of the main busbars and the distribution busbars.
- Form of internal separation required by the project.
- Temperature conditions assumed for the rating.
- Whether the assembly design is verified according to the IEC 61439 series.
How do you account for the short-circuit level?
Use the prospective short-circuit current at the switchboard, taken from a short-circuit study, to define the withstand and breaking capacity of busbars and protective devices. Never size these from the transformer rating alone, since the source arrangement and connected motors change the result.
The short-circuit study is an engineering document that calculates the fault current at each point of the system. It should consider the utility contribution, transformers, cables and motor contribution. Ask which operating arrangement produces the highest fault level, for example transformers in parallel, because that is usually the one that governs.
Also confirm with the designer:
- The fault level used and the arrangement it assumes.
- Duration of the fault the busbars must withstand, tied to protection settings.
- Selectivity between the incomer, couplers and feeders.
- Any planned increase in source capacity that would raise the fault level.
How do you plan spare capacity and future expansion?
Define spare capacity as a written policy: spare feeders, free physical space and reserve capacity in busbars and incomers, agreed with plant management before the design is frozen. Reserve that is not documented tends to disappear during construction.
Distinguish three kinds of reserve:
| Reserve | Meaning | Decision needed |
|---|---|---|
| Equipped spare | Feeder already installed and ready to use | How many, and for which ratings |
| Space spare | Empty compartment or column prepared for a feeder | Where, and with what busbar provision |
| Capacity reserve | Headroom in incomers, busbars and transformers | Which growth scenario it covers |
Also decide whether the switchboard can be extended at the ends, and whether the electrical room has the room to do so. For a broader look at how a plant defines motor feeders, see How to Specify an MCC: Data Your Project Must Define.
What should the calculation report record?
The calculation report should record every input, criterion, assumption and result, so another engineer can reproduce the sizing and check it later. It is the document that links the load list to the final ratings.
A useful report includes:
- Revision of the load list and the date it was received.
- Demand criteria and the operating scenarios considered.
- Single-line diagram revision and source arrangement.
- Short-circuit study reference and the fault level adopted.
- Rated currents, busbar ratings and the conditions behind them.
- Spare and expansion policy, with the quantities reserved.
- Open points and assumptions awaiting confirmation.
Once the sizing is approved, the next stage is manufacturing, described in How to Build a Low-Voltage Switchboard: Assembly Steps. Authomathika is an engineering integrator that works across electrical, automation and industrial panels, and each project is assessed by scope and quote. You can review its electrical solutions or its industrial electrical panels.