Terms of Reference vs Basic Design: Which to Use and When

Terms of reference vs basic design: learn how each document defines scope, when a service needs only a TR, and when works require a basic design.

Direct answer

Terms of reference (TR) describe the need, scope, deliverables and acceptance criteria for a service or supply. A basic design is an engineering document that defines the work well enough to estimate cost and schedule. Use a TR for services and supplies; require a basic design for works and engineering.

Institutional content: Authomathika

Published:

Procurement teams often use "terms of reference" and "basic design" as if they were interchangeable. They are not. Each document answers a different question and demands a different level of definition. Choosing the wrong one leads to vague proposals, disputed scope and change orders.

This guide compares the two by contracting criterion: service versus works and engineering. The terms come from Brazilian public procurement practice (termo de referência and projeto básico), but the logic applies to private industrial contracting as well.

What does each document define?

A terms of reference (TR) is a document that describes what must be delivered, why, under which conditions and how the result will be accepted. A basic design is an engineering document that represents the work or system with enough detail to characterize it, estimate cost and schedule, and let bidders price the same thing.

The practical difference is the level of definition:

AspectTerms of referenceBasic design
Main questionWhat do we need, and how will we judge it?What exactly will be built or installed?
Typical contentObjective, scope, deliverables, schedule, responsibilities, acceptance criteriaDrawings, diagrams, calculations, equipment lists, technical specifications, descriptive memorandum
Prepared byRequesting area, often with engineering supportEngineering, by a qualified professional
Best suited toServices and suppliesWorks and engineering
Risk if weakAmbiguous scope and disputed acceptanceWrong quantities, rework, cost overruns

See Terms of Reference: What They Are and Why They Matter for the document itself, and What Is a Technical Specification and How to Write One for the technical annex that supports both.

Services and supplies: when is a TR enough?

A TR is enough when the result can be described by performance, deliverables and acceptance criteria, without the bidder needing a finished engineering design to price it. Maintenance services, inspections, calibration, standard supplies and technical support usually fit.

A TR works well when:

  • the service repeats a known method, such as periodic inspection or preventive maintenance;
  • the equipment and quantities are already identified in a list or inventory;
  • the outcome is measurable, such as a test report or a restored function;
  • the contractor does not need to design a solution before pricing.

Even then, the TR should be specific. Include the site, the equipment, the interfaces with operations, safety requirements and the documents the contractor must hand over. For a step-by-step method, read How to Write Terms of Reference for an Industrial Service.

Works and engineering: when should you require a basic design?

Require a basic design when the contractor will build, install or modify something whose scope depends on engineering decisions. Without it, bidders fill the gaps with their own assumptions, and proposals stop being comparable.

A basic design is the right requirement when:

  1. the work creates or changes a physical asset, such as a substation, an electrical room or a control system;
  2. quantities, layouts or equipment selection affect cost and schedule;
  3. several disciplines interact, such as electrical, automation and mechanical assembly;
  4. you need a reliable cost estimate before committing to a contract.

In industrial work, a basic design typically brings together one-line diagrams, load lists, equipment specifications, layout drawings, I/O lists and a descriptive memorandum. The Descriptive Memorandum guide explains the narrative part of that package.

The level of detail should be enough to characterize the work, not to replace the detailed design the contractor will produce later. Electrical and automation engineering must be signed by a qualified, licensed professional and follow the applicable standards and the plant's own procedures, in their current editions.

Are they the same thing under Brazil's Law 14.133?

No. Under Law 14.133, the terms of reference and the basic design are distinct instruments with different roles. The TR is associated mainly with the procurement of services and supplies, while the basic design is associated with works and engineering services.

The law defines what each instrument must contain and when it is required. Because these requirements are detailed and subject to regulation and updates, consult the current text of the law, the applicable regulations and your legal department before drafting a public procurement. This guide explains the logic, not the legal requirements item by item.

For private industrial contracting, the law does not bind you, but its distinction is a useful discipline: define the need and acceptance for services, and define the engineering for works.

How do you combine both in industrial contracting?

Use the TR as the contract frame and the basic design as the technical core when a package mixes engineering, supply and field work. The TR states commercial scope, responsibilities and acceptance; the basic design fixes what will physically be delivered.

A practical sequence:

StepDeliverableResponsible
1. Define the need and boundariesDraft TRRequesting area
2. Develop the engineeringBasic design and specificationsEngineering
3. Attach the design to the TRConsolidated bid packageProcurement with engineering
4. Compare proposalsTechnical and commercial analysisEngineering and procurement
5. Define acceptanceTest and commissioning criteriaEngineering and operations

On large packages, such as a turnkey project or a control system migration, the interfaces between disciplines decide the outcome. Engineering EPC is where Authomathika, an integrating engineering company founded in 1999, works on projects, administration, construction and production in a single scope. For a deeper look at what to settle before signing, see the guide on what to define before contracting industrial EPC engineering.

Every contract is evaluated by scope and budget, so the quality of your documents directly shapes the quality of the proposals you receive.

Frequently asked questions

Can I use only a TR for an industrial works contract?
It is risky. Without engineering definition, bidders make their own assumptions about quantities and solutions, and proposals become hard to compare. For works, attach a basic design or at least a consistent set of specifications.
Does a basic design replace the detailed design?
No. The basic design characterizes the work well enough to estimate and compare proposals. The detailed design, produced later, defines what is needed to build and install.
Who should write each document?
The requesting area usually leads the TR, with engineering support. The basic design must be prepared by engineering, signed by a qualified professional where required.
Do private companies need to follow Law 14.133?
No, the law governs public procurement. Private companies can still adopt the same distinction, because it improves clarity, comparability and acceptance.
What happens if the TR and the basic design conflict?
Conflicts create disputes over scope and acceptance. Define an order of precedence among the documents in the contract and review them together before releasing the bid package.